Concepts:
The Lifecycle of Testing
In the software development lifecycle, software is refined through
iterations. In this environment, the testing lifecycle must also have an
iterative approach with each build being a target for testing. Additions and
refinements are made to the tests that are executed for each build, accumulating
a body of tests, which are used for regression testing at later stages. This
approach implies that it causes reworking the tests throughout the process, just
as the software itself is revised. There is no frozen software specification and
there are no frozen tests.

This iterative approach gives a high focus on regression test. Most tests of
iteration X are used as regression tests in iteration X+1. In iteration X+2, you
would use most tests from iteration X and iteration X+1 as regression tests, and
the same principle would be followed in subsequent iterations. Because the same
test is repeated several times, it is well worth the effort to automate the
tests. It becomes necessary to effectively automate your tests to meet your
deadlines.
Look at the lifecycle of testing without the rest of the project in the same
picture. This is the way the different activities of testing are interconnected
if you view them in a non-iterative view:

The testing lifecycle.
This lifecycle has to be integrated with the iterative approach, which means
that each iteration will have a test cycle following that pattern.

Execution is both execution of the new tests and
regression tests using previous tests.
The testing lifecycle is a part of the software lifecycle; they should start
at the same time. The design and development process for tests is as complex and
arduous as the application being built. If not started early enough, the tests
will either be deficient, or cause a long testing and bug-fixing schedule to be
appended to the development schedule, which defeats the goals of iterative
development. Furthermore, the test planning and design activities can expose
faults or flaws in the application definition. The earlier these are resolved,
the lower the impact on the overall schedule. Problems found during evaluation
can be solved within this iteration, or postponed to the next iteration. One of
the major tasks in evaluation is to measure how complete the iteration is by
verifying what requirements have been implemented. There is always some
"requirements creep" from iteration to iteration, something you need
to be aware of and able to manage.
The ways in which you will perform tests will depend on several factors: your
application domain, your budget, your company policy and risk tolerance, and
your staff. How much you invest in testing depends on how you evaluate quality
and tolerate risk in your particular environment.